Licensed builders manage the entire process, including cost estimates, home design collaboration with the customer, permits, site preparation, ordering the home from Affinity, finishing, and final inspections.

Local approved licensed contractors are necessary to complete construction on your property and provide accurate new home construction costs for your area. The total cost of a new home is more than just the house – it also includes things like:

  1. Site Preparation & Land Costs Vary Widely – Affinity only manufactures the home modules in a factory. Foundation work, grading, driveways, septic systems, wells, and utility hookups vary significantly depending on location and must be managed by a licensed builder or contractor.
  2. Local Building Codes & Permits Differ – Each city or county has its own permitting fees, inspection requirements, and code compliance costs. Only a licensed builder working in that area can accurately estimate these.
  3. Onsite Construction – This can include garages, decks, walkways, screen rooms, pools, and more. Your builder can incorporate these into the overall project cost.
  4. Legal & Contractual Limitations – Only licensed home builders can provide complete turnkey pricing and legally sign construction contracts.

Traditional home construction

  • The image shown may be from a week into construction
  • All building materials are delivered to the job site
  • Building materials are exposed to all weather, meaning the home interior may be wet during construction
  • The GC hires subcontractors to frame the home, install the roof, windows, doors, and siding
  • The GC hires more subcontractors to finish the interior drywall, flooring, electrical, and plumbing

Modular home construction

  • GC completes the foundation.
  • While the site and foundation are being readied, the home is in the manufacturing process
  • No building materials are delivered to the job site 
  • 80%-90% of the home is already done at Affinity’s manufacturing facility
  • Note how clean and organized the property is. 
  • The modular home is delivered to the property in a protective wrap

Modular home construction (a few hours later)

  • Same home as seen to the left
  • Same day and in just a few hours, the modular home is on the foundation and weather-tight
  • Note windows, doors and siding (painted) already installed

Modular home construction (a couple of weeks later)

  • Same home as seen to the left
  • Deck rails, metal roof, and stairs completed on-site

What is completed on-site by the GC?

  • Foundation
  • Utilities – water, drainage, electrical
  • Interior painting, install flooring, lighting
  • Attached and detached garages
  • Porches, patios and decks (if not integrated in the initial floor plan design
  • Driveway and sidewalks
  • Lawn and landscaping

The Manufacturing Process

Our homes are constructed rain or shine in a controlled environment using the same building materials shown in the traditional construction picture above.